Timing of the works: 
• Localised pre-works are due to start 11th March 2025 for 
approximately 4 working days. 
• Works will take place during the day between 08:00 – 16:00. 
• The works will be followed by a second surface dressing 
treatment to the whole road during April/May (which will 
take approximately 2 hours) followed by a sealant 
approximately 4 days later (4 hours).  Further information 
including dates will be communicated at a later date. 
• Advance warning boards with start and end date will be 
erected before works commence. 
Works Information  
• 08:00 – 16:00 (on each day / weekdays only) 
• Guyers Road, Freshwater – from Victoria Road to Gate Lane (area of works 
marked in red on the attached plan). 
Time of works 
Safety measures 
during works: 
• A 24-hour road closure will be required at all times throughout the works for 
safety reasons. 
• Vehicle access will be prohibited at all times within the area of works. 
• Only when it is safe to do so, resident access will be maintained within the road 
closure extent outside of the area of works. 
• Should you require your vehicle during the dates of work we would recommend 
parking in an alternative location. 
• “No Parking” cones will be placed out the night prior to works commencing. 
• Pedestrian access will be maintained. 
• Emergency vehicle access will be maintained.
Island Roads schedule of works for the Freshwater Bay area.

Timing of the works: 
• Localised pre-works are due to start 13th March 2025 for 
approximately 3 working days. 
• Works will take place during the day between 08:00 – 16:00. 
• The works will be followed by a second surface dressing 
treatment to the whole road during April/May (which will 
take approximately 2 hours) followed by a sealant 
approximately 4 days later (4 hours).  Further information 
including dates will be communicated at a later date. 
• Advance warning boards with start and end date will be 
erected before works commence. 
Works Information  
• 08:00 – 16:00 (on each day / weekdays only) 
• Guyers Road, Freshwater – from Victoria Road to Gate Lane (area of works 
marked in red on the attached plan). 
Time of works 
Safety measures 
during works: 
• A 24-hour road closure will be required at all times throughout the works for 
safety reasons. 
• Vehicle access will be prohibited at all times within the area of works. 
• Only when it is safe to do so, resident access will be maintained within the road 
closure extent outside of the area of works. 
• Should you require your vehicle during the dates of work we would recommend 
parking in an alternative location. 
• “No Parking” cones will be placed out the night prior to works commencing. 
• Pedestrian access will be maintained. 
• Emergency vehicle access will be maintained.
Island Roads schedule of works for the Freshwater Bay area.

Timing of the works: 
• Localised pre-works are due to start W/C 17th March 2025 for 
approximately 2 working days. 
• Works will take place during the day between 08:00 – 16:00. 
• The works will be followed by a second surface dressing 
treatment to the whole road during April/May (which will 
take approximately 2 hours) followed by a sealant 
approximately 4 days later (4 hours).  Further information 
including dates will be communicated at a later date. 
• Advance warning boards with start and end date will be 
erected before works commence. 
Works Information  
• 08:00 – 16:00 (on each day / weekdays only) 
• Victoria Road, Freshwater – from Guyers Road to Bedbury Lane Freshwater 
(area of works marked in red on the attached plan). 
Time of works 
Safety measures 
during works: 
• A 24-hour road closure will be required at all times throughout the works for 
safety reasons. 
• Vehicle access will be prohibited at all times within the area of works. 
• Only when it is safe to do so, resident access will be maintained within the road 
closure extent outside of the area of works. 
• Should you require your vehicle during the dates of work we would recommend 
parking in an alternative location. 
• “No Parking” cones will be placed out the night prior to works commencing. 
• Pedestrian access will be maintained. 