Skip to content

NEWPORT ROAD, FRESHWATER & FRESHWATER ROAD, SHALFLEET

 

CARRIAGEWAY PRE-WORKS NEWPORT ROAD, FRESHWATER & FRESHWATER ROAD, SHALFLEET 
We are writing to let you know about the carriageway improvement works due to take place in your local 
area shortly, and to provide you with some information and guidance in relation to what will happen 
during the works, to enable you to plan accordingly. During this work no on-street parking and no vehicle 
through access will be permitted within the areas of closure. 
We recognise that these improvement works may cause some inconvenience for residents and 
businesses, but we hope any disruption will be offset by the long-term improvements we are making.  We 
would like to thank you in advance for your assistance in enabling us to complete these works. 
Please note, there are a variety of factors including inclement weather and emergency works that may 
affect the timing of works. Please watch the on-site boards for confirmation/changes of the start date / 
duration (example shown below). 
Timing of the works: 
• Localised pre-works are due to start W/C 10th March 2025 for 
approximately 15 working days. 
• Works will take place during the day between 09:00 – 15:30. 
• These works will be completed in three phases. 
• The works will be followed by a second surface dressing 
treatment to the whole road during April/May (which will 
take approximately 2 hours) followed by a sealant 
approximately 4 days later (4 hours).  Further information 
including dates will be communicated at a later date. 
• Advance warning boards with start and end date will be erected before works commence.
Phase 1 
• Newport Road, Freshwater - various localised areas between Afton Road and 
Wilmingham Lane. 
Phase 2 
• Newport Road, Freshwater - various localised areas between Wilmingham Lane 
and the main Tapnell Farm entrance road. 
Phase 3 
• 09:00 – 15:30 (on each day / weekdays only) 
• Freshwater Road, Shalfleet – various localised areas between the main Tapnell 
Farm entrance road and approx 250m east. 
Time of works 
Safety measures 
during works: 
• A road closure will be required at all times throughout the works for safety 
reasons. 
• Vehicle access will be prohibited at all times within the area of works. 
• Only when it is safe to do so, resident access will be maintained within the road 
closure extent outside of the area of works. 
• Should you require your vehicle during the dates of work we would recommend 
parking in an alternative location. 
• “No Parking” cones will be placed out the night prior to works commencing. 
• No pedestrians or cyclists through route. 
• Emergency vehicle access will be maintained.
DECORATIVE IMAGE